Maldives Transport and Contracting Company (MTCC) has mobilized to Gaaf Dhaal atoll Gahdhoo for a harbor development project.
According to the state-owned enterprise, mobilization took place on 07 May 2022, Saturday.
The project scope involves dredging and excavation operations of 23,017 cubic meters of sand volume, construction of harbor structures including a 232 meters breakwater, 35 meters revetment, 320 meters quay wall and a 320 meters scouring apron.
Additional components of the project include construction of walkway bridges (26 x 2 meters), along with the installation of a 1,600 square meters harbor pavement. Miscellaneous components of the project include installation of harbor lights.
Meanwhile, MTCC reported that the total value of the project was MVR38.4 million.
MTCC mobilizes to Gahdhoo harbor development site
Fetched On
Last Updated
Last Updated